Road base calculator for Montana
Figure lane and pad material from the finished depth, where a few inches can add ten tons.
Enter your project dimensions
For a 100-foot lane that is 10 feet across and 6 inches deep after compaction, plan on about 31 tons of road base. Lane quantities add up fast, and free delivery is especially useful when 30 tons would otherwise cost nearly as much to haul as the material. Road base combines graded crushed stone with fines and weighs about 3,000 lb per cubic yard. It compacts into a firm layer for roads, driveways, and equipment yards. Where specifications permit, this calculation also applies to recycled crushed concrete base.
Lane calculations
- For lanes, take the centerline length and average the width. For pads, multiply length by width.
- Allow 4 inches compacted for light residential use, 6 for regular traffic and delivery trucks, and 8-12 beneath equipment or on soft subgrade.
- Divide cubic feet by 27 for yards; multiply by 1.5 for tons; leave +10% for compaction.
Quick figure: one ton ≈ 36 sq ft at 6" compacted
Coverage and lane totals
| Compacted depth | 1 ton covers | Tons per 100 ft of 10-ft lane |
|---|---|---|
| 4 inches | ≈ 54 sq ft | 20.4 |
| 6 inches | ≈ 36 sq ft | 30.6 |
| 8 inches | ≈ 27 sq ft | 40.7 |
| 12 inches | ≈ 18 sq ft | 61.1 |
Building a lane for the next winter
- Clear away organic material before placing the base. Putting stone over topsoil lets mud work upward through it, regardless of how deep the layer is.
- Lay woven geotextile first where the subgrade is wet or soft, then place the stone. It adds useful reinforcement to a lane at low cost.
- Keep each lift at 4 inches or less and roll it before adding the following lift.
- Build a 2-3% crown away from the centerline so water drains off the edges instead of entering the base.
- For a neat travel surface with less dust, finish with #57 or driveway gravel.
- Moving 20-plus tons by hand can take a week. Budget for a skid steer or a tractor with a box blade, which can handle the work in an afternoon.
Example: a 100-foot farm lane
At 6 inches, one hundred by ten feet works out to 1,000 x 0.5 = 500 cubic feet = 18.5 cubic yards, or about 28 tons and 30-31 after allowing for compaction. Plan on two tandem loads. Put two drop points along the lane instead of one pile at the gate, so material is closer to where it needs spreading.
Pads for RVs, containers, and equipment
Use the same calculation for pads, but choose depth for axle weight rather than the calendar. A 12 x 40 RV pad at 6 inches compacted needs about 12 tons. A 20 x 40 equipment yard at 8 inches takes 27. Shipping containers put their load on four corners, so use a full 8 inches plus fabric for container pads, even on sound ground, to limit corner settlement by spring.
Recycled concrete road base
Virgin road base and recycled concrete base use the same calculation. Recycled concrete can compact and carry load similarly, and may cost less. Check county requirements first, since some specifications call for virgin aggregate. For private lanes and pads, use the same 1.5 tons per yard, lift placement, and crown.
Road base by ton or lane
How can I determine the road base I need?
What coverage comes from 1 ton of road base?
What is the weight of 1 yd of road base?
How deep should road base be for a driveway?
Road base versus crusher run
Is fabric needed below road base?
Other calculators
Road base order information.
For lane-size orders, road base is priced by the ton and delivered free, since hauling is often the largest expense.